CAMP
Reconstruction / new construction of bridges on the roads to high mountain pastures
Bridge location: |
The bridge is located in Karakol canyon.
Corresponding number on the general plan: № 72.
Administrative area: National nature park of Karakol.
River name: Karakolka |
Actual condition of the bridge/road |
The bridge has being constructed |
Coverage of high mountain pastures |
|
Actual users on the location |
|
Other potentialities for the use of the location |
|
Bridge operation |
|
Project budget review |
Budget item |
Costs in US$ |
Machinery: |
629,00 |
Wood (was supplied by local forestry) |
1026,00 |
Materials: |
77,00 |
Overheads: |
51,00 |
Wages: |
965,00 |
Travel: |
50,00 |
Development and survey works: |
400,00 |
Total: |
3198,00 |
Exchange rate of Som/US$: 39,00/1
Costs were covered by users themselves account for US1411,00$ |
Project evaluation by the CAMP |
Appendix |
- Location plan (outline)
- Detailed budget in soms
- Additional photographs
- Agreement regarding the activities to be implemented by users themselves
|
|