Actual condition of the bridge/road
|
The bridge bearing pillar and the span construction have been fully destroyed. The laid down logs provide passing. New construction is required.
|
Coverage of high mountain pastures
|
The road and the bridge cover 4 000 ha of woodlands and mountain pastures. It is used for grazing, haying and logging. The entire territory is located at 2 200 m above sea level.
|
Actual users on the location
|
The main bridge users are: Ak-Terek aiyl okmotu, Jety-Oguz aiyl okmotu, local community of Kichi-Jargylchak village.
The total number of the main users is 5 farms.
|
Other potentialities for the use of the location
|
With the bridge and road being repaired there will be new potentialities for bee keeping, harvesting of medicinal herbs,berries and mushrooom, the development of tourism and stock-breeding.
|
Bridge operation
|
The daily carrying capacity of the bridge is 10 cars (Niva, UAZ), trucks of 15 tons, four – five times a year the bridge is used for livestock migration, it is also used for passers-by and horse riders. |
Budget review
|
Budget item
|
Costs in US$
|
Machinery: |
601 |
Materials: |
708 |
Overheads: |
372 |
Planned accumulations: |
395 |
Wages: |
304 |
Taxes: |
682 |
Travel: |
190 |
Development and survey works: |
650 |
Total:
|
3902
|
Exchange rate of som/US$: 48/1
Costs to be covered by users themselves account for 692$ |
Project evaluation by the CAMP
|
Appendix
|
- Location plan (outline)
- Detailed budget in soms
- Additional photographs
- Agreement regarding the activities to be implemented by users themselves
|