CAMP

Reconstruction / new construction of bridges on the roads to high mountain pastures

 

 

Bridge location:

The road from Karakol town to Echkili-Tash village (Sary-Jaz) of Ak-Suu rayon.

Corresponding number on the general plan: ¹ 29.

Name of aiyl okmotu: Karakol aiyl okmotu.

River name: Sary-Jaz.




Actual condition of the bridge/road

The bridgeway is not suitable for the further operation (cross-bars and flooring are decayed). It is required to replace the cross-bars and flooring.

Coverage of high mountain pastures

The road and the bridge cover about 3 800 ha of high mountain pastures. The location is used for grazing. The entire location is at 3 000 m above sea level.

Actual users on the location

The main users of the bridge are: Karakol aiyl okmotu, frontier troops, a weather station and individual stock-breeders of Ak-Suu rayon.

The total number of the main users is 8 farms.

Other potentialities for the use of the location

With the bridge and the road being improved there will be potentialities: for stockbreeding, harvesting of medicinal herbs, tourism and tourist hunting.

Bridge operation

The daily carrying capacity of the bridge and the road is 5 cars (Niva, UAZ), trucks of 15 tons, four – five times a year the bridge is used for livestock migration, it is also used for passers-by and horse riders.

 

Budget review

Budget item

Costs in US$

Machinery:

251

Materials:

451

Overheads:

229

Planned accumulations:

212

Wages:

178

Taxes:

361

Travel:

105

Development and survey works:

358

Total:

2145

 

 

Exchange rate of som/US$: 48/1

Costs to be covered by users themselves account for 170$

Project evaluation by the CAMP

Appendix

  1. Location plan (outline)
  2. Detailed budget in soms
  3. Additional photographs
  4. Agreement regarding the activities to be implemented by users themselves