Reconstruction / new construction of bridges on the roads to high mountain pastures

 

Bridge location:

The road to Novo-Voznesenovka village along Boz-Uchuk canyon of Ak-Suu rayon.

Corresponding number on the general plan: ¹ 25.

Name of aiyl okmotu: Boz-Uchuk aiyl okmotu.

River name: Boz-Uchuk.




Actual condition of the bridge/road

A wooden bridge of 5 m length with wooden bearing pillars being decayed; temporary laid down logs provide passing. New construction is required.

Coverage of high mountain pastures

The road covers about 3 000 ha of woodlands and high mountain pastures. The location is used for grazing, haying and logging. The entire location is at 2 300 m above sea level.

Actual users on the location

The main users of the bridge are: Boz-Uchuk aiyl okmotu, Ak-Suu forestry, inhabitants of Boz-Uchuk Enchilesh villages.

The total number of the main users is 6 farms.

Other potentialities for the use of the location

With the bridge and the road being improved there will be potentialities: for beekeeping, stockbreeding, harvesting of medicinal herbs and tourism.

Bridge operation

The daily carrying capacity of the bridge and the road is 10 cars (Niva, UAZ), trucks of 15 tons, four – five times a year the bridge is used for livestock migration, it is also used for passers-by and horse riders.

 

 

 

Budget review

Budget item

Costs in US$

Machinery:

601

Materials:

708

Overheads:

372

Planned accumulations:

395

Wages:

304

Taxes:

682

Travel:

190

Development and survey works:

650

Total:

3902

 

 

Exchange rate of som/US$: 48/1

Costs to be covered by users themselves account for 415$

Project evaluation by the CAMP