Reconstruction / new construction of bridges on the roads to high mountain pastures

 

Bridge location:

The road from Ak-Suu village to Ak-Suu forestry of Ak-Suu rayon.

Corresponding number on the general plan: № 23.

Name forestry: Ak-Suu research forestry.

River name: Lesnoe.




Actual condition of the bridge/road

The existing pipe of 1m diameter is entirely silted with a few logs being laid down as a temporary bridgeway. The diameter of the pipe should be increased.

Coverage of high mountain pastures

The road and the bridge cover about 40 ha of woodlands. The location is used as a forest tree nursery. There are coniferous varieties of trees from three continents. The entire location is at 2 500 m above sea level.

Actual users on the location

The main user of the bridge is Ak-Suu research forestry.

The total number of the main users is 1 forestry.

Other potentialities for the use of the location

With the bridge being improved there will be potentialities to improve the recreation area and the forest tree nursery.

Bridge operation

The daily carrying capacity of the bridge is 10 cars (Niva, UAZ), it is also used for passers-by and horse riders.

 

 

 

Budget review

Budget item

Costs in US$

Machinery:

249

Materials:

333

Overheads:

98

Planned accumulations:

99

Wages:

76

Taxes:

227

Travel:

43

Development and survey works:

224

Total:

1348

 

 

Exchange rate of som/US$: 48/1

Costs to be covered by users themselves account for 313$

Project evaluation by the CAMP

Appendix

  1. Location plan (outline)
  2. Detailed budget in soms
  3. Additional photographs
  4. Agreement regarding the activities to be implemented by users themselves