CAMP

Reconstruction / new construction of bridges on the roads to high mountain pastures

 

 

Bridge location:

Road from Saruu village along Juukuchak canyon

Corresponding number on the general plan: ¹ 12.

Name of aiyl okmotu : Saruu aiyl okmotu.

River name: Juuku




Actual condition of the bridge/road

A wooden bridge of 5 m length has been destroyed, a new construction is required.

Coverage of high mountain pastures

The road and the bridge cover 5 000 ha of woodlands and mountain pastures. It is used for grazing, haying and logging. The entire territory is located at 2 300 m above sea level.

Actual users on the location

The users of the bridge are: Saruu aiyl okmotu, local shepperds and tourists.

The total number of main users is 7 farms.

Other potentialities for the use of the location

With the bridge and road being repaired there will be new potentialities for bee keeping, harvesting of medicinal herbs, tourism and stock-breeding.

Bridge operation

The daily carrying capacity of the bridge is 15 cars (Niva, UAZ), trucks of 15 tons, four – five times a year the bridge is used for livestock migration, it is also used for passers-by and horse riders.

 

 

 

 

 

Budget review

Budget item

Costs in US$

Machinery:

601

Materials:

708

Overheads:

372

Planned accumulations:

395

Wages:

304

Taxes:

682

Travel:

190

Development and survey works:

650

Total:

3902

 

 

Exchange rate of som/US$: 48/1

Costs to be covered by users themselves account for 368$

Project evaluation by the CAMP

Appendix

  1. Location plan (outline)
  2. Detailed budget in soms
  3. Additional photographs
  4. Agreement regarding the activities to be implemented by users themselves